(5)

a programme to cover this year and next year, hoping

that by so doing the expenditure will to a great

extent be spread out so as to be met by the surplus

of revenue over expenditure anticipated.

14.

The improvements required are as follows :-

Estimated Cost.

$

1.

The provision of an additional 200 ft mast at D'Aguilar with foundations.

17000

2. Sundry alterations to buildings

and additional buildings

16100

3.

Additions to Power Plant

12860

4.

#

##

5.

#

Transmitting Plant Receiving Gear

93400

9000

6. Provision of automatic transmitter

5280

7. Additional Power & Telephone Cables

9000

8. Alterations to Radio Counter

1000

9. Tools and Instruments

1600

$165240

The total cost and division of cost of the

above items over a period o: two years is :-

Estimated Total To be expended of present

proposal

$165240

during 1928.

$68790

To be expended during 1929.

$96450

Of the $68790 estimated for 1928, the expenditure

would become due approximately as follows :-

April

$1000

May

$3000

June

$6100

July

14000

Aug.

16040

Sept.

1600

Nov.

2250

Dec.

24000

$68790.